IS 12800 : Part 3 : 1991 Guidelines for Selection of Hydraulic Turbine, Preliminary Dimensioning and Layout of Surface Hydroelectric Power Houses - Part 3 : Small, Mini and Micro Hydroelectric Power Houses

UDC 621.311.21 (026) WRD 15
Reaffirmed 2018

1 Scope

1.1 This standard lays down the guidelines for the selection of hydro turbine preliminary dimensioning and layout of small, miniand micro hydroelectric power houses.

1.2 It is presumed that the data with regard to design head,design discharge, number and types of units and capacity are known. Departure from these guidelines may be necessary to meet thespecial requirements and conditions of individual site.

2 Reference

IS 4410 : Part 10 :1987 Glossary of terms relating to river valley projects :Part 10 Hydro-electric power station including water conductor system