1 Scope

This standard (Part 3) covers the minimum requirements for pre-commissioning and commissioning of natural gas pipeline, including pre-commissioning activities such as pre-commissioning checks, flushing, dewatering, swabbing, magnetic cleaninglelectronic geometry pigging (EGP), drying, inertisation, gas-in and commissioning, stabilization and 72 h run.

2 Reference

The standard given below contains provision which through reference in this text, constitutes provision of this standard, At the time of publication, the edition indicated was valid. All standards are subject to revision and parties to agreements based on this standard are encouraged to investigate the possibility of applying the most recent edition of the standard indicated below:

     IS No.       Title
IS 15663 ( Part 1) : Design and installation of natural
     2006 gas pipelines - Code of practice :
Part 1 Laying of pipelines