IS 9913 : 2000 Code of Practice for Construction of Cross Drainage Works

ICS 93.160 WRD 13
Reaffirmed 2013

1 Scope

The construction of a cross drainage works of a large sizeincorporates numerous activities, each of which, in turn, may haveto be planned and executed considering several practical aspects.It may not be possible to cover all such situations in a singlestandard. This standard, therefore, gives broad guidelines for theplanning and construction of cross drainage works.

2 References

IS 383 :1970Coarse and fine aggregates from naturalsources for concrete

IS 456 :1978Code of practice for plain andreinforced concrete

IS 1343 :1980Code of practice for prestressedconcrete

IS 1888 :1971Method of load tests on soils

IS3370Code of practice for concrete structurefor the storage of liquids:

Part 1 :1965General requirements

Part 2 :1967Reinforced concrete structures

Part 3 :1967Prestressed concrete structures

Part 4 :1967Design tables

IS 3558 :1983Code of practice for use of immersionvibrators for consolidating concrete

IS 4082 :1996Stacking and storage of constructionmaterials and components at site -Recommendations

IS 4410 : Part 15 : Sec 5 :1992 Glossary of terms relating to rivervalley projects:Part 15 Canal structures,Section 5 Cross drainage works

IS 5624 :1993Foundation bolts

IS 7784 : Part 1 :1993Code of practice for designing of crossdrainage works :Part 1 General features

IS 7784 : Part 2 : Sec 3 :1996 Code of practice for design of crossdrainage works :Part 2 Specific requirements,Section 3 Canal syphons

IS 9103 :1979Specifications for admixtures forconcrete

IS 9795 : Part 1 :1981Guidelines for the choice of the typeof diversion works:Part 1 Coffer dams