IS 9913 : 2000 Code of Practice for Construction of Cross Drainage Works
ICS 93.160 | WRD 13 |
|
Reaffirmed 2013 |
1 Scope
The construction of a cross drainage works of a large sizeincorporates numerous activities, each of which, in turn, may haveto be planned and executed considering several practical aspects.It may not be possible to cover all such situations in a singlestandard. This standard, therefore, gives broad guidelines for theplanning and construction of cross drainage works.
2 References
IS 383 :1970Coarse and fine aggregates from naturalsources for concrete
IS 456 :1978Code of practice for plain andreinforced concrete
IS 1343 :1980Code of practice for prestressedconcrete
IS 1888 :1971Method of load tests on soils
IS3370Code of practice for concrete structurefor the storage of liquids:
Part 1 :1965General requirements
Part 2 :1967Reinforced concrete structures
Part 3 :1967Prestressed concrete structures
Part 4 :1967Design tables
IS 3558 :1983Code of practice for use of immersionvibrators for consolidating concrete
IS 4082 :1996Stacking and storage of constructionmaterials and components at site -Recommendations
IS 4410 : Part 15 : Sec 5 :1992 Glossary of terms relating to rivervalley projects:Part 15 Canal structures,Section 5 Cross drainage works
IS 5624 :1993Foundation bolts
IS 7784 : Part 1 :1993Code of practice for designing of crossdrainage works :Part 1 General features
IS 7784 : Part 2 : Sec 3 :1996 Code of practice for design of crossdrainage works :Part 2 Specific requirements,Section 3 Canal syphons
IS 9103 :1979Specifications for admixtures forconcrete
IS 9795 : Part 1 :1981Guidelines for the choice of the typeof diversion works:Part 1 Coffer dams